Visit our new photo album on Flickr! https://flic.kr/s/aHBqjCjPRn

Scarlet Oak School Project Update 6/18/2025
*updated* Project Schedule as of 6/18/2025: PDF
Scarlet Oak School Project Update 6/16/2025
We did have an additional update here, but it was lost due to a restore of the website - our apologies!
We’re excited to share that construction has officially begun on the Scarlet Oak School expansion project! This marks a major milestone in our commitment to growing and improving our campus for current and future generations of students. As with any construction project, there will be some unavoidable disruptions including dust, noise, and increased activity around the site. But these are all signs of meaningful progress! The field and playground will be closed until the remodel and addition is completed in August of 2026. Signage will also be going up this week. This summer, the grounds will be escavated, the foundations poured, and walls going up on the two new additions. Meanwhile, inside the "short" hallway (north-south hallway) is being renovated. Our staff and students will enjoy some new refreshed spaces this Fall. This past week, asbestos abaitment was completed along with some demolition starting. Our operations and Pandas are removing custodial items, technology cables, and WiFi to ensure we have room for new items. It's a team effort!
To help manage the impact, site fencing will be fully installed by Thursday, June 19th, clearly marking the construction zone and helping to ensure safety for everyone on our grounds. Street sweepers will also be used regularly in an effort to minimize dust, though we know windy days can make that a challenge. We appreciate your patience as we work through these temporary inconveniences.
ComEd, Astound, and Comcast are all in the process of relocating their utility lines to accommodate the construction footprint. This work includes the installation of new utility poles and the rerouting of both aerial and underground lines. The design and execution of these relocations are based on engineering plans developed by ComEd, as the work is taking place within their easements. As such, ComEd is responsible for determining the placement and method of relocation, and coordinating with the other service providers to ensure everything is done safely and efficiently.
A dedicated project manager from Cordigan is on-site every day, overseeing operations and ensuring that all subcontractors are following safety protocols and compliance standards. Their presence helps keep the project running smoothly and responsibly. The district is also involved and will be on site daily to ensure progress.
We’re grateful for your support and understanding as we build something truly special for our Cardinals and community!
Here are some recent pictures:
Scarlet Oak School Project Update 3/19/2025
We are excited to invite you to the groundbreaking ceremony for the SOS project on March 20, 2024, at 1:30 PM outside at Scarlet Oak School. This significant event will feature our Superintendent, Dr. Sala, and Assistant Superintendent, Mr. Ziegler. We are also pleased to welcome Dave Termunde, our Project Manager, along with our board members, architects, and other distinguished guests. Join us as we celebrate the start of this transformative project, marking a new milestone for our community.
Scarlet Oak School Project Update 2/20/2025
The slide deck that was presented to the Board of Education is located here.
Scarlet Oak School Project Update 2/13/2025
For the Scarlet Oak project, we will not have a General Contractor (GC) overseeing the project. Instead, a Construction Manager from Cordogan Clark will be in charge. This change allows for greater control, oversight, and visibility of the project. Additionally, it enables the district to receive better bids without the extra markups from a GC.
The bids for the Scarlet Oak addition and renovation were due on December 19th. On that date, Cordogan Clark and the Business Office conducted the bid opening. Cordogan Clark has reviewed the lowest bidders, performed due diligence, and selected the recommended companies for each construction area. The bid packages were presented to the Board of Education for approval on January 10, 2025. While some bids were higher and some lower, the overall costs align with our projected budget. This means that the 4th grade will remain at Scarlet Oak, and grades 1-4 will be housed there for the fall of 2026. We have spent months meticulously planning the building details to ensure cost-effectiveness while maintaining quality.
Additionally, Jewel-Osco generously donated $150,000 to Scarlet Oak School to cover the cost of the new playground. We are grateful for this donation, which will benefit our students and community for generations. The playground will be age-appropriate for our 1st-4th grade students to enjoy during recess.
One of our biggest challenges in breaking ground on time is the location of the ComEd utility poles that run through our property. These poles also contain Comcast, Astound, and AT&T lines that are in the process of being relocated.
In the summer of 2025, we will add temporary parking for staff to use for the next school year. Since we plan to break ground in March/April (weather permitting), we will utilize street parking for the remainder of the school year.
Scarlet Oak School Project Update 12/12/2024
The Scarlet Oak School renovation and addition has gone out to bid this week! The bid notice is located here. Arbor Park SD 145 (hereinafter referred to as the Owner) will receive multiple prime contract bids for the following project until 2:00 pm, local time, on December 19, 2024, at 17301 S. Central Avenue, Oak Forest, Illinois 60452.
Scarlet Oak School, built in 1964, stands as a testament to the community’s commitment to education but now requires significant updates to meet the needs of today’s learners. The benefits of this project are substantial. These improvements will make the school safer and more secure, extend the useful life of the facility, reduce emergency repair costs, enhance ADA accessibility, create classrooms equipped for modern instructional technology, and provide an inviting and efficient environment for students and staff.
The goals of these updates are fourfold:
- Enhance Safety and Security: Create safer and more secure learning environments by upgrading building access with secure vestibules and improved infrastructure.
- Improve Air Quality and Comfort: Provide air conditioning throughout the school, addressing air quality, ventilation, and energy efficiency to ensure a comfortable and healthy learning environment.
- Optimize Space Utilization: Address overcrowding by reconfiguring spaces to support both current needs and future growth, providing students with an environment that fosters learning and collaboration.
- Update Critical Infrastructure: Replace outdated mechanical, plumbing, electrical, and Heating, Ventilation, and Air Conditioning (HVAC) systems, while completing state-mandated repairs to ensure the building remains functional and compliant for years to come.
By addressing these critical areas, we are not only preserving Scarlet Oak School’s legacy but also ensuring it remains a cornerstone of educational excellence in our community. This project will be in multiple phases, allow construction to start while school is still in session.
- Phase 1 will be breaking ground for the additions in Spring 2025.
- Phase 2 will be the "short hallway" (South hallway) classroom remodel in Summer 2025.
- Phase 3 will be the "long hallway" (east-west hallway) classroom remodels in Summer 2026.
- The entire building tentatively is scheduled to be completed for August 2026.
Project Drawings and Documents
As we continue through this journey over the next two years, we will post a monthly update video. This will show planning and progress!
Scarlet Oak School Project Update 5/30/2024
Thank you for your patience while we got our ducks in a row for the new Scarlet Oak! Over the last few years, we’ve had a variety of projects where we used Green Associates as our architects. To better align with our vision and budget, we researched new firms and the Board of Education selected Cordogan Clark for our Scarlet Oak project. This partnership better aligns with our vision to create the best facility for our staff and students.
As we’ve been saving for this project, with construction costs continuously rising and not going down, it’s best to do a complete renovation on the existing building along with an addition. Engineers looked at the building and the bones are great! The renovation would include refreshed classrooms, cabinetry, windows, and most importantly mechanical including plumbing, HVAC, and electrical.
Over the past few years, the construction industry has been a tough market to navigate. When the conversations of a new Scarlet Oak School began before COVID, the cost per square foot for construction was under $250. Then, like other industries, construction costs began to rise. From $350 per square foot in 2021-22, to $500-600 per square foot for new construction that we are currently seeing now. This has made us reassess our plans for Scarlet a couple of times.
Due to Arbor Park School District’s current debt structure, there is currently a flexibility available for the financing of this project. The Board of Education could finance this project without the requirement of a referendum and with minimal or no impact on the taxpayer. That is the goal of our school board. However, to do this, the district must stick to a hard budget for this project, which can present a challenge with the current market conditions. Due to this limitation, this will determine if Scarlet will be grades 1-3 or 1-4. This all depends on construction costs at the time of the bid opening. We are going for 1-4, but if needed and to stay fiscally responsible, grades 4-8 will be housed at APMS. As we have with past projects, we will get creative in funding alternative sources such as grants and incentive programs.
Here is the projected timeline:
- October 2024, out to bid
- December 2024, BOE approval
- February 2025, start new construction
- 2 summers (Summer ’25 and ’26) of renovations in the old space
- August 2026, open entire building (renovated and new).
Thank you!
Dave & Andrew